| Performance Measures |
Budget Standard 2008/09 |
Performance to 30 June 2009 |
| Output class 1: Building Regulation and Control To provide regulatory and control services for the building industry under the Building Act 2004 and related consumer information |
Output 1.1: Set Standards for Building
Maintaining and reviewing existing Building Code and Compliance Documents; issuing warnings and bans as required |
| 1.1.1 Quantity |
|
|
| Undertake five programmes of work to develop Building Code Compliance Documents or guidance documents |
Five programmes of work undertaken |
Achieved
Amendments to Compliance Documents or guidance completed for:
- fire standards
- indoor environment
- structure
- energy efficiency
- Department of Conservation's backcountry huts.
|
| Programmes undertaken in accordance with the requirements of the Building Act 2004 and the Department's quality standards for policy advice |
Quality standards met |
Achieved
All programmes of work have undergone internal review, and meet the quality standards.
|
| Output 1.2: Implement the Review of the Building Code |
| 1.2.1 Quality |
|
|
| Implement the findings of the review of the Building Code, as instructed by the Minister |
Findings of review implemented |
Achieved
The findings of the review were implemented through the development of a fire safety framework, and Compliance Documents for Department of Conservation huts and simple housing.
|
| Policy development is undertaken in accordance with the Department's quality standards for policy advice. |
Quality standards met |
Achieved
All programmes of work have undergone internal review and meet the quality standards.
|
| Output 1.3: Sector Advice and Guidance Provide information, advice and guidance to the building sector on the new regulatory schemes under the Building Act 2004 |
| 1.3.1 Quantity |
|
|
| Information on building standards, Code compliance and product certification is available and awareness campaigns conducted |
Information provided and awareness campaigns conducted |
Achieved
Information is available (by website and hard copy) and awareness campaigns are conducted as required. For example, during 2008/09 information campaigns for product certification and thermal insulation were delivered.
|
| Provide guidance on the achievement of Building Code compliant buildings |
Guidance provided |
Achieved
All changes to the Building Code and/or Compliance Documents were issued with the applicable guidance, for example energy efficiency guidance
|
| Respond to technical queries from local authorities and the building sector |
Responses provided |
Achieved
Responses were provided to enquiries received through the Building Controls 0800 number and email.
|
| 1.3.2 Quality |
|
|
| Information provided on time and developed in accordance with the Department's guidelines on professional communication |
Guidelines met |
Achieved |
| Output 1.4: Operate Regulatory Schemes Administer product certification scheme |
| 1.4.1 Quantity |
|
|
| Product certification: Develop and operate the product certification scheme. |
Scheme developed and operating |
Achieved
The regulations are in place and the scheme has been operational since November 2008. Three applications for product certification are being processed.
|
| 1.4.2 Quality |
|
|
| Measures for product certification scheme to be developed on establishment of finalised scheme |
Measures developed |
Achieved |
| All operational policy development meets our quality standards for policy advice |
Quality standards met |
Achieved
All programmes of work have undergone internal review, and meet the quality standards.
|
| Output 1.5: Resolve Disputes Investigate and resolve disputes about territorial local authorities and issue determinations |
| 1.5.1 Quantity |
|
|
| Disputes1 received and managed |
Demand-driven |
Achieved
133 determinations were received and managed.
|
| Determinations issued (demand-driven) |
160 |
Below forecast demand
116 determinations were issued (the budget standard of 160 was an estimated figure, as these are demand-driven).
|
| 1.5.2 Quality |
|
|
| Percentage of determinations successfully appealed |
Less than 2% |
Achieved
None successfully appealed.
|
| Percentage of determinations subject to clarification |
Less than 3% |
Achieved
2.6% were subject to clarification.
|
| 1.5.3 Timeliness |
|
|
| Percentage of determinations completed within the statutory timeframe (60 days) without agreement of the parties to extend timeframes |
95% |
Achieved
98% (average number of days is 38).
|
| Output 1.6: Building and Construction Monitoring, Research and Evaluation Undertake regulator and industry performance monitoring and reporting, and commission building-related research |
| 1.6.1 Quantity |
|
|
| Four industry advisory panels operating |
Ongoing |
Achieved
Advisory Panels for Access, Fire, Structure and Building Envelope met with the Department on a regular basis to advise on trends and issues.
|
| Programmes of research undertaken to support the setting of standards |
Programmes undertaken |
Achieved
The following research projects are under way.
- Commercial building energy end use study (BEES) - year two of six years' work has been completed.
- Fire performance research to support the development of a fire safety framework is on track for completion in March 2010.
- Research into an option for a single timber framing treatment hazard class is on track and due for completion in September 2010.
- Effectiveness of paint on remedial timber treatments for leaky houses is on track and due for completion in October 2010.
- An initial investigation into a commercial building energy rating scheme (BERS) has been completed. Recommendations will be prepared by November 2009.
- Investigation into extreme snow loadings was completed by 30 June 2009.
|
| Implement the strategic research programme |
Ongoing |
The development of the research strategy took longer than expected; particularly the work involved and time required to consult with the sector. A draft strategy has been developed and will be finalised in 2009/10. |
| 1.6.2 Quality |
|
|
| Industry advisory panels operate within their agreed terms of reference |
Terms of reference met |
Achieved |
| Research projects completed in accordance with the terms of reference |
Terms of reference met |
Achieved |
| Output 1.7: Advice and Guidance Provide information, advice and guidance to the sector |
| 1.7.1 Quantity |
|
|
|
Provide local authorities information, advice and guidance on:
- Dam Safety Scheme
- Licensed Building Practitioner Interface
- Building Consent Authority functions
- Infringement Scheme
|
Information, advice and guidance provided |
Achieved
Publication of the following guidance, along with advice and guidance made available on the Department's website.
- Guidance document disseminated to councils about new Infringement Scheme in August 2008.
- BCA Update (accreditation and building control) guidance documents published in August, October and December 2008.
- Dam Safety Scheme: Guidance to regional authorities and owners of large dams in September 2008.
- Dam Safety Scheme: An overview for rural owners of large dams in September 2008.
- Schedule 1 (exempt building work) guidance material provided to building sector in October 2008.
- Phase 2 Accreditation (Quality Assurance) guidance material provided to councils in November 2008.
- Guidance document disseminated to councils and practitioners about changes to Schedule 1 of the Building Act (exempt building work) in November 2008.
- Amendments to building consents guidance material provided to sector in November 2008.
- National training course in phase 2 accreditation requirements delivered to all building consent authorities in November and December 2008.
- Assessment of alternative solutions guidance material provided to building sector in December 2008.
- Non-load bearing timber guidance provided to the sector in December 2008.
- A beginner's guide to building consent and resource consent processes provided to sector in June 2008.
|
| Provide the building sector and consumers with information, guidance and advice through: Codewords issues Call centre enquiries (demand-driven) |
10 12,000 |
Achieved 10 issues published. Above forecast demand 14,374 enquiries received (demand-driven). |
| 1.7.2 Quality |
|
|
| All communications developed in accordance with our guidelines on professional communication |
Guidelines adhered to |
Achieved |
| Percentage of queries resolved by call centre (not escalated) |
70% |
Not achieved 67% |
| Output 1.8: Building Sector Skills and Education Improving sector skills through training and education |
| 1.8.1 Quantity |
|
|
| Support development of National Qualification for Building Officials |
Qualification development supported |
Achieved Supported the Local Government Industry Training Organisation-led development of two National Qualifications: National Diploma in Building Control Surveying (Small Buildings) National Diploma in Building Control Surveying (Medium and Large Buildings). |
| 1.8.2 Quality |
|
|
| National qualification meets NZQA requirements |
NZQA requirements met |
Achieved National Diploma in Building Control Surveying (Small Buildings) and National Diploma in Building Control Surveying (Medium and Large Buildings) qualifications registered on the qualifications framework. |
| Output 1.9: Consent Authority Performance Improve the performance of Local Government Consent Authorities |
| 1.9.1 Quantity |
|
|
| Undertake and complete technical reviews of territorial authorities |
5 |
Achieved
Technical reviews completed for the following territorial authorities.
- Bay of Plenty Council cluster (four councils - Tauranga, Rotorua, Taupo and South Waikato District Councils)
- Northland councils (three councils - Far North, Kaipara and Whangarei District Councils)
- Queenstown Lakes District Council
- Selwyn District Council
- Thames-Coromandel District Council
|
| Operate Building Consent Authority accreditation and registration scheme |
Scheme operated |
Achieved
Scheme operated as intended.
All councils who applied for phase 1 accreditation achieved it and have been registered as building consent authorities.
|
| Monitor performance of accreditation body against appointment agreement |
Agreement met |
Achieved
Agreement met. Ongoing operational performance discussions held and monitoring occurring through:
- monthly performance and project planning/implementation meetings with International Accreditation New Zealand (IANZ)
- consistency workshops, which are undertaken quarterly to ensure shared understanding of accreditation requirements between IANZ and the Department
- review of IANZ performance reports:
- Feb - Jun 08 report received and response provided September 2008
- Jul - Sep 08 report received and response provided November 2008
- Oct 08 - Jan 09 report received and response provided February 2009
- independent review of phase 1 of accreditation scheme, including IANZ's role and performance, completed March 2009, and disseminated to relevant stakeholders in May 2009.
|
| Investigate and resolve complaints about territorial and building consent authorities |
Demand-driven |
Achieved
22 formal complaints about building consent authorities were received and investigated between July 2008 and June 2009. Of these:
- 19 showed no evidence of negligence or failure on the part of the building consent authority in the performance of a statutory building control function, although opportunities for performance and customer service improvements were identified
- one related to Resource Management Act issues and the complainant was referred to the Ministry for the Environment
- one complainant elected not to continue with the complaint
- one council was found to have been negligent and failed to perform a statutory building consent authority function. The council involved has:
- improved its business processes, which have been independently audited
- been accredited as a building consent authority.
|
| 1.9.2 Quality |
|
|
| Technical reviews completed in accordance with the Department's Technical Review Guidelines |
Guidelines adhered to |
Achieved |
| Complaints resolved in a timely manner and in accordance with departmental policy |
Departmental policy met |
Achieved |
| Evaluation criteria developed for the effectiveness of accreditation scheme |
Evaluation criteria developed |
Achieved |